Miaowei Dam

Dam in Dali Bai Autonomous Prefecture, Yunnan
25°51′15.66″N 99°9′40.78″E / 25.8543500°N 99.1613278°E / 25.8543500; 99.1613278PurposePowerStatusOperationalConstruction began2010Owner(s)Lancang River CompanyDam and spillwaysType of damEmbankment, rock-fillImpoundsLancang (Mekong) RiverHeight139.8 m (459 ft)Length576.7 m (1,892 ft)Width (crest)12 m (39 ft)ReservoirTotal capacity660,000,000 m3 (540,000 acre⋅ft)Catchment area93,900 km2 (36,300 sq mi)Commission date2017-2018TypeConventionalTurbines4 x 350 MW Francis-typeInstalled capacity1,400 MWAnnual generation5,990 GWh (expected)

The Miaowei Dam is a rock-filled embankment dam on the Lancang (Mekong) River in Yunlong County of Yunnan Province, China. Construction on the dam began in 2010. The four turbines of 1,400 MW hydroelectric power station were commissioned in 2017 and 2018.[1][2][3][4]

See also

  • flagChina portal
  • iconWater portal
  • iconRenewable energy portal

References

  1. ^ "Introduction of Miao tail power plant construction (苗尾电站建设情况简介)" (in Chinese). Chinese Communist Yunlong County. 1 September 2013. Retrieved 16 June 2014.
  2. ^ "Yunnan Lancang River Hydropower Miao tail excitation system equipment tenders" (in Chinese). China Huaneng Group. 20 January 2014. Archived from the original on 7 January 2015. Retrieved 17 June 2014.
  3. ^ "A Waterfight Like No Other May be Brewing over Asia's Rivers". Bloomberg.com. November 2016.
  4. ^ "苗尾水电站". www.chng.com.cn (in Chinese). Archived from the original on 2019-03-20. Retrieved 2019-12-27.